Roseland Rotary Room Project
Peter Claver House
 
Roseland Rotary is ready to start on the first room remodeling in the Peter Claver House.
 
 
#1     Replace bad flooring in attic area above the room.
#2     Repair walls for dry walling the ceiling.
#3     Repair Floor
#4     Repair windows.
#5     Install insulation in ceiling.
#6     Sand and putty windows as needed, prepare for paint.
#7     Sand and putty trim and doors as needed, prepare for painting
#8     Drywall walls as needed and closet.
#9     Repair plaster where needed.
#10   Paint walls, trim and doors.
#11   Prepare and sand down floor.
#12   Finish floors.
 
 
 
 
Work Schedule
A crew of 8 working in two man teams.
  1. Attic flooring repairing
  2. Ceiling preparing for drywall
  3. Repair floor
  4. General cleanup
 
Saturday August 29, 2015,                     12:00PM  to ?
Tuesday September 1, 2015                     6:00PM to ?
Thursday September 3, 2015                   6:00PM to ?
Saturday September 5, 2015                  10:00AM to ?  ND Night Game
 
 
Materials
 
#1     Lumber, including flooring, drywall, plaster and paint.
#2     Insulation
#3     Paint
#4     Floor Finish
#5     Other odds and ends
 
 
Labor
 
#1     Rotarians
#2     Possibly pay a plaster guy