After receiving approval from the Sunshine Coast Regional District and the Department of Fisheries for the design of a salmon viewing platform in John Daly Park Jon Paine jumped into action with his design and ordered the the materials to be delivered. Suddenly with the delivery date set we needed to dig and set forms for the concrete foundations. Then Jon arranged for concrete to be donated only to realize that the truck could not get under the park sign. A quick call and leonard Lee built a liner for his pick up truck and saved the day moving concrete from the delivery truck to the forms. Fill was donated and then a group of community volunteers came out and working with Jon's well laid out cutting list and plans cut and assembled the platform in one morning. Sue Paine came out and cooked hamburgers for the volunteers.Image
 
 