Originally there were 15employees. This rose to a maximum of 62 and has now settled at 45.
One of their biggest contracts has been at Marina Terrace in Wanaka. This was supposed to be a two-year development and is now just finished after five years.
Clutha Concrete is a subsidiary of Andrew Haulage – they guarantee to deliver concrete 24 hours a day. This year they have delivered 4203 cu meters – 1100 loads.
Chipping Plant – they have two big chippers working all year round. They supply Silver Fern with 3 loads of chips per day for their boilers.

This year Colin’s son, Troy, won the national excavator competition, for a second time.

The biggest risk for the company now is Covid. They are finding it difficult to get parts and prices are increasing rapidly. Colin gave an example of a part that three months ago cost $270, now costing $580. Cement has gone up 15% in the last month – it is all imported.
Thank you, Colin, for a very interesting talk.